Numerical values

No. Year Location Wells Depths Diameter Expansion Qspez before hydropuls® Qspez after hydropuls®
1 2012 Vennesla – Norwegen Nr. 1 20 m 400 mm Steel slotted bridge 9,43 m3/hm 19,15 m³/hm
2 2015 Oslo – Asker Norwegen DRB 17‐509 200 m 140 mm Open hole 0,79 m³/hm 3,80 m³/hm
3 2018 Wien‐Österreich Nr. 4 66 m 350/225 mm Steel 1,59 m³/hm 8,95 m³/hm
4 2019 Glogow ‐ Polen Nr. 12 51 m 315/280 mm PVC 1,35 m³/hm 3,95 m³/hm
5 2019 Ostrava Nová Ves ‐ Tschechien St‐5 24 m 400 mm Wire wrapped screen 9,81 m³/hm 35,22 m³/hm
6 2024 Allyneety ‐ Irland Nr. 1 184 m 254/152 mm Open hole 0,05 m³/hm 0,33 m³/hm
7 2025 Strahovice ‐ Tschechien HV‐1 20 m 300 mm PVC 0,93 m³/hm 7,91 m³/hm
To top